What was signed
On 2 September, FHR-Illinois LLC, a subsidiary of Full House Resorts, and the City of Waukegan signed Amendment No. 1 to their development agreement. The original was dated 18 January 2023.[1]
Waukegan is a city on Lake Michigan, about 40 miles north of Chicago. The casino is called American Place.[1]
Three things changed. The deadline to finish the permanent casino moved to 17 February 2029, with trading to start within three months of that. The company may keep using the temporary casino for five years beyond the permanent opening. And parts of the project design, including possible later phases, were revised.[1]
The clause the city fought for
Where the original said "thirty-six (36) months following the Operations Commencement Date (Phase 0)", the amendment strikes that wording out and puts 17 February 2029 in its place.[2]
Look at what changed there. A countdown that begins when something else happens will drift every time that something else drifts. A calendar date will not. Waukegan gave up three years and took a fixed deadline in exchange. It is the only thing in this document the city clearly won.

The tent
The temporary casino includes what the amendment calls the Sprung Structure. That is a brand of tensioned fabric building — a large, engineered tent.
Under the new terms it must be removed no later than five years after the permanent casino starts trading.[2]
Run that forward. Trading started in the temporary building in 2023, the permanent casino has until May 2029 at the outside, and the tent may remain for five years past that. On those terms it comes down some time around 2034, having been put up as a stopgap eleven years earlier.
Put the two periods from the contract side by side and something odd falls out. The deadline the city originally set for finishing the permanent casino was shorter than the grace period the tent now gets after that casino opens.
Why the delay happened, in the company's own account
The amendment blames a court case. Waukegan Potawatomi Casino, LLC v. Illinois Gaming Board produced adverse rulings that, in the parties' words, created substantial uncertainty and materially impeded the developer's ability to advance design, financing and construction.[2]
Both sides recorded their agreement that this amounted to force majeure under section 16 of the original contract.[2] That is the commercially significant clause, because a deadline covered by force majeure can move without either party having failed.
The amendment then tracks the project restarting. A revised site plan cleared the city on 2 September 2025. Earthmoving and grading were approved the following April, on the 13th, and the company broke ground on 3 June 2026.[2]

Why this is worth your attention
Temporary casinos are now a standard opening move in the United States. A developer wins a licence, puts up a modular building or a tent, starts taking money within a year, and funds the permanent resort out of the cash flow.
The pitch to a city council is that the temporary building is a bridge. This amendment is what the bridge looks like after three years of trouble: still standing, contracted to stand for eight more, and with the permanent building's deadline pushed into 2029.
If you are advising a municipality on one of these agreements, the clause to read is the one governing how long the temporary facility may operate after the permanent one opens. That is where the risk sits, and in Waukegan's case it is five years.
What the filing does not tell you
No cost figure for the permanent casino, and no revised budget.[1]
No statement of what the temporary casino earns, so there is no way to judge from this document whether keeping it open is a convenience or the plan.
And no explanation of the deferred boutique hotel fee the amendment creates,[2] beyond its existence. A deferred fee is a payment somebody agreed to wait for.
Sources
- Full House Resorts, Inc. — Form 8-K, Item 1.01 (filed 8 September 2026 for an event dated 2 September 2026, English). That FHR-Illinois, LLC and the City of Waukegan, Illinois entered into Amendment No. 1 to the Development and Host Community Agreement dated January 18, 2023, relating to the American Place casino; that the amendment formalised revisions discussed and approved by the Waukegan City Council in July 2026; that it extends the construction completion date of the permanent facility to February 17, 2029 with operations commencing within three months of completion; that it permits retention and use of the temporary casino structure for a period of five years beyond the opening of the permanent casino; and that it revises certain project details including potential future phases.
- Full House Resorts, Inc. — Exhibit 10.1: Amendment No. 1 to Development and Host Community Agreement (dated 2 September 2026, English). The amendment itself: that Section 4.1.b.ii.A is amended by deleting "thirty-six (36) months following the Operations Commencement Date (Phase 0)" and replacing it with "February 17, 2029"; that the Sprung Structure forming part of the Temporary Facility shall be removed no later than five years following the Operations Commencement of Phase 1 unless the City approves otherwise in writing; that adverse rulings in Waukegan Potawatomi Casino, LLC v. Illinois Gaming Board created substantial uncertainty and materially impeded the developer's ability to advance the design, financing, construction and development of the permanent facility, and that both parties agreed these constituted force majeure events under Section 16; that the City approved a site plan on September 2, 2025 and earthmoving, grading and related site work on April 13, 2026; that the developer held a groundbreaking on June 3, 2026; that the development property comprises an approximately 31.7 acre city-owned parcel at 600 Lakehurst Road and two developer-owned parcels of approximately 10 acres at 4001-4011 Fountain Square Place; and that the amendment creates a Deferred Boutique Hotel Fee.